Roads22PE0151

REHABILITATION (COMPLLETION) OF ROAD ALONG SITIO LUCBUBAN TO MANIT-TOKTOK FOOTPATH, POBLACION, ITOGON, BENGUET

REHABILITATION (COMPLLETION) OF ROAD ALONG SITIO LUCBUBAN TO MANIT-TOKTOK FOOTPATH, POBLACION, ITOGON, BENGUET is a DPWH-tracked public work in Benguet 1st DEO, Cordillera Administrative Region. Reported contract value: ₱2,935,488.00. Status: Reported complete (DPWH). Contractor on record: NINETY ONE BUILDERS. Figures trace to dpwh.

Benguet 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Ambalanga River (Below Vital Fianza Jr Residence), Supang, Poblacion, Itogon, Benguet
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Benguet 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,935,488.00

Progress

Reported complete (DPWH)

Start Date

December 19, 2022

Target End

April 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.