Roads25N00125

CABADBARAN - PUTING BATO - LANUZA ROAD, PACKAGE 12, SURIGAO DEL SUR

CABADBARAN - PUTING BATO - LANUZA ROAD, PACKAGE 12, SURIGAO DEL SUR is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱163,854,012.14. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: J M LUCIANO CONST INC 2083. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱163,854,012.14

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 21, 2025

Target End

November 17, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.