GAA 2025 DA FMR25GP0055

CONCRETING OF BRGY. JAMBAD TO BRGY. TINAYTAYAN FMR, BRGY. JAMBAD AND BRGY. TINAYTAYAN, DUMARAO, CAPIZ

CONCRETING OF BRGY. JAMBAD TO BRGY. TINAYTAYAN FMR, BRGY. JAMBAD AND BRGY. TINAYTAYAN, DUMARAO, CAPIZ is a DPWH-tracked public work in Capiz 2nd DEO, Region VI. Reported contract value: ₱14,919,592.80. Status: Past target date (DPWH On-Going). Contractor on record: 7 JL HARDWARE. Figures trace to dpwh.

Capiz 2nd DEO, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Facilities along Panay/Mambusao River Basin, Tico River Control, Panay, Capiz
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Capiz 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,919,592.80

Progress

Past target date (DPWH On-Going)

Start Date

June 6, 2025

Target End

December 16, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.