Roads24IC0163

CONCRETING OF BRGY. TAGUITE TO BRGY. MAGCASUANG FMR PHASE IV, BRGY. TAGUITE AND BRGY. MAGCASUANG, BABATNGON, LEYTE

CONCRETING OF BRGY. TAGUITE TO BRGY. MAGCASUANG FMR PHASE IV, BRGY. TAGUITE AND BRGY. MAGCASUANG, BABATNGON, LEYTE is a DPWH-tracked public work in Leyte 1st DEO, Region VIII. Reported contract value: ₱34,769,325.62. Status: Past target date (DPWH On-Going). Contractor on record: C N E CONST 22148. Figures trace to dpwh.

Leyte 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure ( Drainage System ) , Phase 2, Barangay Canhidoc, Palo, Leyte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Leyte 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱34,769,325.62

Progress

Past target date (DPWH On-Going)

Start Date

October 4, 2024

Target End

April 21, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.