Buildings and Facilities19EH0096

CONSTRUCTION OF MULTI - PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER), MABINI, SAN FERNANDO, ROMBLON

CONSTRUCTION OF MULTI - PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER), MABINI, SAN FERNANDO, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱4,312,440.00. Status: Reported complete (DPWH). Contractor on record: ASHLEYKA CONST AND SUPPLIES 41140. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱4,312,440.00

Progress

Reported complete (DPWH)

Start Date

August 1, 2019

Target End

February 20, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.