Roads25DC0157

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, REHABILITATION OF ROADS LOCATED AT SAN MIGUEL (TANGKE ROAD) STO.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, REHABILITATION OF ROADS LOCATED AT SAN MIGUEL (TANGKE ROAD) STO. is a DPWH-tracked public work in Batangas 3rd DEO, Region IV-A. Reported contract value: ₱14,465,461.00. Status: Past target date (DPWH On-Going). Contractor on record: RGE CONST AND SUPPLY INC FORMERLY:R G EVANGELISTA CONST AND SUPPLY. Figures trace to dpwh.

Batangas 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure in the City of Calaca, Batangas
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Batangas 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

68 projects · ₱374.3M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, IMPROVEMENT OF ROAD, BRGY. TAYSAN-BRGY. PALANCA, SAN JOSE, BATANGAS

Batangas 4th DEO, Region IV-A

2023₱24.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF ROAD, MUNICIPALITY OF SAN PASCUAL, BATANGAS

Batangas 2nd DEO, Region IV-A

2022₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, GULIBAY, BAUAN, BATANGAS

Batangas 2nd DEO, Region IV-A

2024₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY INICBULAN, B

Batangas 2nd DEO, Region IV-A

2024₱14.0M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FOUR (4) STOREY FOUR (4) WORKSHOP BUILDING AT TAYSAN NHS, SAN JOSE, BATANGAS

Batangas 4th DEO, Region IV-A

2017₱13.4M
Reported complete (DPWH)
No sat.

OPENING AND CONCRETING OF BRGY. MANALUPANG FMR, BRGY. MANALUPANG, BAUAN, BATANGAS

Batangas 2nd DEO, Region IV-A

2022₱9.9M
Reported complete (DPWH)
View all 68 projects →

4. Implementation

Contract Amount

₱14,465,461.00

Progress

Past target date (DPWH On-Going)

Start Date

June 2, 2025

Target End

October 29, 2025

5. Audit