Flood Control and Drainage21KL0023

CONSTRUCTION OF FLOOD CONTROL AT GITAGUM RIVER (DOWNSTREAM) ALONG GITAGUM BRIDGE, MISAMIS ORIENTAL

CONSTRUCTION OF FLOOD CONTROL AT GITAGUM RIVER (DOWNSTREAM) ALONG GITAGUM BRIDGE, MISAMIS ORIENTAL is a DPWH-tracked public work in Misamis Oriental 2nd DEO, Region X. Reported contract value: ₱64,201,450.00. Status: Reported complete (DPWH). Contractor on record: MAMSAR CONST AND INDUSTRIAL CORP. Figures trace to dpwh.

Misamis Oriental 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱10,183,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Gingoog River Downstream, Gingoog City, Misamis Oriental
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Misamis Oriental 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

124 projects · ₱7.4B total · 0 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF FLOOD MITIGATION STRUCTURE ALONG MAOYON RIVER, BRGY. MAOYON (LS), PTO. PRINCESA CITY, PALAWAN

Region IV-B, Region IV-B

2024₱241.2M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENAMNCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS- CONST. OF FLOOD MITIGATION STRUCTURE ALONG MAOYON RIVER (RS), STA. 000+000-STA. 000+623.17, PTO. PRINCESA CITY, PALAWAN

Region IV-B, Region IV-B

2024₱241.2M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS, DAPA PORT - CONSUELO - STA. CRUZ - STA. FE - LBERTAD - CABITOONAN - CATANGNA - GENERAL LUNA ROAD (INCL. BRIDGE COMPLETION OF CATANGNAN - CABITOONAN BRIDGE AND LIBERTAD BRIDGE 2), SURIGAO DEL N

Region XIII, Region XIII

2018₱193.0M
Reported complete (DPWH)
No sat.

DAPA PORT-CONSUELO-CORAZON-STA. CRUZ - STA. FE - CABITOONAN-CATANGNAN-GENERAL LUNA ROAD (CABITOONAN-CATANGNAN BRIDGE PHASE II), SURIGAO DEL NORTE 1ST LD., GENERAL LUNA, SURIGAO DEL NORTE, SIARGAO ISLANDS

Region XIII, Region XIII

2017₱193.0M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED), DINAGAT-LORETO ROAD, K0009+466-K0010+000, K0010+000-K0010+757, K0048+000-K0048+700, K0053+020-K0053+320, K0053+348-K0054+000-K0055+000, K0058+566-K0058+810, DINAGAT ISLANDS

Region XIII, Region XIII

2017₱161.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF EMBARKADERO FLOOD CONTROL STRUCTURE ALONG BAHAY RIVER, (DOWNSTREAM), PALO, LEYTE

Region VIII, Region VIII

2024₱159.6M
Past target date (DPWH On-Going)
View all 124 projects →

4. Implementation

Contract Amount

₱64,201,450.00

Progress

Reported complete (DPWH)

Start Date

February 23, 2021

Target End

November 14, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.