Construction of Flood Mitigation Structure22CE0126

Construction of Flood Control Structure along Labong River, Brgy. Villarosa (Phase 5), Licab, Nueva Ecija

Construction of Flood Control Structure along Labong River, Brgy. Villarosa (Phase 5), Licab, Nueva Ecija is a DPWH-tracked public work in LICAB (NUEVA ECIJA), NUEVA ECIJA, Region III. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: NIÑAS CONST CORP FORMERLY: NINA'S CONST AND SUPPLIES / SOLFIO P JACINTO CONST INC. Figures trace to sumbong.

LICAB (NUEVA ECIJA), NUEVA ECIJA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Banco River, Brgy. Macapsing, Rizal, Nueva Ecija
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002994

₱533,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002434

₱107,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002435

₱99,100,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002803

₱30,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002818

₱3,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

April 5, 2022

Target End

February 28, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.