Buildings and Facilities17FF0168

CONSTRUCTION OF ONE (1) UNIT SENIOR HIGH SCHOOL UNIQUE WORKSHOP BUILDING (BUILDING B), GOA NATIONAL HIGH SCHOOL, GOA, CAMARINES SUR

CONSTRUCTION OF ONE (1) UNIT SENIOR HIGH SCHOOL UNIQUE WORKSHOP BUILDING (BUILDING B), GOA NATIONAL HIGH SCHOOL, GOA, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 4th DEO, Region V. Reported contract value: ₱3,825,149.72. Status: Reported complete (DPWH). Contractor on record: PARTIDO CONST. Figures trace to dpwh.

Camarines Sur 4th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

134 projects · ₱5.3B total · 0 flags

Other projects by this contractor

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY GUINACUTAN, VINZONS, CAMARINES NORTE, VI

Region V, Region V

2024₱198.0M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING PRIMARY ROADS, DAANG MAHARLIKA, K0251+800.00-K0251+887.00; K0251+1048-K0252+700.00; K0252+750.00-K0254+040.00, CAMARINES NORTE

Region V, Region V

2019₱115.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MISSING LINK/NEW ROAD,LALUD - GARCHITORENA ROAD STA.5+713.73 - STA.10+809.63 LAGONOY, CAMARINES SUR

Camarines Sur 4th DEO, Region V

2020₱106.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MISSING LINK/NEW ROAD,(P00402351LZ)LAGONOY-CARAMOAN ROAD SECTION 1: STA.4+390.90 - STA.6+327.41 SECTION 2: STA.7+640.90 - STA.8+204.39 LAGONOY SECTION, CAMARINES SUR

Camarines Sur 4th DEO, Region V

2020₱100.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0277+000-K0278+956, K0278+994-K0279+225, LABO, CAMARINES NORTE (1ST LEGISLATIVE DISTRICT)

Region V, Region V

2025₱100.2M
Past target date (DPWH On-Going)
No sat.

REHAB./RECONST./UPGRADING OF DAMAGED PAVED ROADS ALONG TIGAON-GOA-SAN JOSE-LAGONOY-GUIJALO VIA SAN VICENTE ROAD K0573+089.00 - K0575+000.00; K0575+233.00 - K0575+522.00; K0575+522.00 - K0575+824.00; K0575+895.00 - K0576+1120.00 CARAMOAN, CAMARINES SUR

Camarines Sur 4th DEO, Region V

2024₱96.5M
Reported complete (DPWH)
View all 134 projects →

4. Implementation

Contract Amount

₱3,825,149.72

Progress

Reported complete (DPWH)

Start Date

December 27, 2017

Target End

March 26, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.