Flood Control and Drainage24AI0264

CONSTRUCTION OF REINFORCED BANK PROTECTION STRUCTURE WITH SHEETPILE ALONG AGNO AND ALLIED RIVER AT ROSALES, PANGASINAN (PACKAGE 1)

CONSTRUCTION OF REINFORCED BANK PROTECTION STRUCTURE WITH SHEETPILE ALONG AGNO AND ALLIED RIVER AT ROSALES, PANGASINAN (PACKAGE 1) is a DPWH-tracked public work in Pangasinan 3rd DEO, Region I. Reported contract value: ₱0.00. Status: Ongoing (DPWH-reported) (For Procurement (DPWH-reported)). Contractor on record: Contractor not linked in this database. Figures trace to dpwh.

Pangasinan 3rd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Banila and Allied River in Barangay Gonzales - Sta. Maria, Umingan, Pangasinan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Pangasinan 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱0.00

Progress

For Procurement (DPWH-reported)

Start Date

Data not yet available

Target End

Data not yet available

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.