Roads23NI0030

ACCESS ROAD LEADING TO TOURISM ENTERPRISE ZONE (TEZ) -RIZAL PORT LEADING TO TURTLE ISLAND, CABGAN & VANISHING ISLAND, BRGY. SUA, BAROBO, SURIGAO DEL SUR

ACCESS ROAD LEADING TO TOURISM ENTERPRISE ZONE (TEZ) -RIZAL PORT LEADING TO TURTLE ISLAND, CABGAN & VANISHING ISLAND, BRGY. SUA, BAROBO, SURIGAO DEL SUR is a DPWH-tracked public work in Surigao del Sur 2nd DEO, Region XIII. Reported contract value: ₱2,448,704.63. Status: Reported complete (DPWH). Contractor on record: LM CONST AND GEN MARKETING. Figures trace to dpwh.

Surigao del Sur 2nd DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tago River, Brgy. Libas Gua, San Miguel, Surigao del Sur
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Surigao del Sur 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

176 projects · ₱2.2B total · 0 flags

4. Implementation

Contract Amount

₱2,448,704.63

Progress

Reported complete (DPWH)

Start Date

February 9, 2023

Target End

March 2, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.