Bridges16AE0020

REHAB./MAJOR REPAIR OF PERMANENT BRIDGES ALONG BACNOTAN-LUNA-BALAOAN RD.,MARAGAYAP BRIDGE

REHAB./MAJOR REPAIR OF PERMANENT BRIDGES ALONG BACNOTAN-LUNA-BALAOAN RD.,MARAGAYAP BRIDGE is a DPWH-tracked public work in La Union 1st DEO, Region I. Reported contract value: ₱13,945,362.92. Status: Reported complete (DPWH). Contractor on record: CHIARA2300 INC. Figures trace to dpwh.

La Union 1st DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Purok 1, Brgy. Pagdaraoan, San Fernando, La Union 1st LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Agency-level releases for FY2016, not tied to this contract

La Union 1st DEO · SARO 2,111 (₱111,347,307,043.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱13,945,362.92

Progress

Reported complete (DPWH)

Start Date

February 4, 2016

Target End

May 3, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.