GAA 2025 SSP25CG0160

BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAN NICOLAS ES, ARAYAT, PAMPANGA

BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAN NICOLAS ES, ARAYAT, PAMPANGA is a DPWH-tracked public work in Pampanga 1st DEO, Region III. Reported contract value: ₱6,576,753.83. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: BPDG CONST CORP FORMERLY: BPDG CONST. Figures trace to dpwh.

Pampanga 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Pampanga River, (Downstream-Left Bank), Barangay Consuelo, Macabebe, Pampanga
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Pampanga 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

115 projects · ₱668.8M total · 0 flags

Other projects by this contractor

View all 115 projects →

4. Implementation

Contract Amount

₱6,576,753.83

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

July 3, 2025

Target End

October 6, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.