GAA 2025 LFP25JG0043

CONSTRUCTION OF DPWH ZAMBOANGA DEL SUR 2ND DEO COMPOUND, BARANGAY POBLACION, GUIPOS, ZAMBOANGA DEL SUR

CONSTRUCTION OF DPWH ZAMBOANGA DEL SUR 2ND DEO COMPOUND, BARANGAY POBLACION, GUIPOS, ZAMBOANGA DEL SUR is a DPWH-tracked public work in Zamboanga del Sur 2nd DEO, Region IX. Reported contract value: ₱39,184,999.47. Status: Past target date (DPWH On-Going). Contractor on record: GENETIAN BUILDERS AND ENT INC FORMERLY: GENETIAN BUILDERS. Figures trace to dpwh.

Zamboanga del Sur 2nd DEO, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱23,400,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Barangay Baclay, Tukuran, Zamboanga del Sur
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Zamboanga del Sur 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱39,184,999.47

Progress

Past target date (DPWH On-Going)

Start Date

March 28, 2025

Target End

October 3, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.