Roads23I00063

CLUSTER 18: 1. ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - BAGAHUPI - BABATNGON - STA. CRUZ - BARUGO - CARIGARA RD., - (S00066LT) K0928+442 - K0928+500, K0928+571 - K0928+673; 2.

CLUSTER 18: 1. ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - BAGAHUPI - BABATNGON - STA. CRUZ - BARUGO - CARIGARA RD., - (S00066LT) K0928+442 - K0928+500, K0928+571 - K0928+673; 2. is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱245,108,022.87. Status: Reported complete (DPWH). Contractor on record: EZJONES CONST INC. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

287 projects · ₱36.2B total · 7 flags

Other projects by this contractor

View all 287 projects →

4. Implementation

Contract Amount

₱245,108,022.87

Progress

Reported complete (DPWH)

Start Date

May 9, 2023

Target End

March 3, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.