Flood Control and Drainage24CC0155

CONSTRUCTION OF CONCRETE SLOPE RIVER WALL ALONG BOCAUE RIVER, BARANGAY BAMBANG, BOCAUE, BULACAN

CONSTRUCTION OF CONCRETE SLOPE RIVER WALL ALONG BOCAUE RIVER, BARANGAY BAMBANG, BOCAUE, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱47,520,281.08. Status: Past target date (DPWH On-Going). Contractor on record: FLORDES CONST. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Balagtas River, Barangay San Juan, Purok 4 - Purok 5, Balagtas, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bulacan 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

333 projects · ₱17.6B total · 0 flags

4. Implementation

Contract Amount

₱47,520,281.08

Progress

Past target date (DPWH On-Going)

Start Date

March 1, 2024

Target End

October 26, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.