Construction of Flood Mitigation Structure23BB0039

Construction of Flood Control Structure along Cagayan River, L. Adviento, Gattaran, Cagayan

Construction of Flood Control Structure along Cagayan River, L. Adviento, Gattaran, Cagayan is a DPWH-tracked public work in GATTARAN (CAGAYAN), CAGAYAN, Region II. Reported contract value: ₱48,980,000.00. Status: Reported complete (DPWH). Contractor on record: TJMT CONST. Figures trace to sumbong.

GATTARAN (CAGAYAN), CAGAYAN, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Cagayan River, L. Adviento, Gattaran, Cagayan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cagayan 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,980,000.00

Progress

Reported complete (DPWH)

Start Date

February 21, 2023

Target End

November 10, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.