Roads18CL0046

ROAD WIDENING- SECONDARY ROADS- OLONGAPO- BUGALLON ROAD- K0225+400- K0226+405, MASINLOC, ZAMBALES

ROAD WIDENING- SECONDARY ROADS- OLONGAPO- BUGALLON ROAD- K0225+400- K0226+405, MASINLOC, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱28,698,917.26. Status: Reported complete (DPWH). Contractor on record: A C SOLIVEN CONST. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Shore Protection at Lapaz, San Narciso, Zambales
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0022785

₱0.00 · FY2018

Released to Division of Zambales (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱28,698,917.26

Progress

Reported complete (DPWH)

Start Date

April 13, 2018

Target End

October 9, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.