Roads20PF0038

IMPROVEMENT OF ROAD, LOO LANAS, PUSONG, BUGUIAS, BENGUET

IMPROVEMENT OF ROAD, LOO LANAS, PUSONG, BUGUIAS, BENGUET is a DPWH-tracked public work in Benguet 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱4,663,874.91. Status: Reported complete (DPWH). Contractor on record: MAKK BUILDERS 36414. Figures trace to dpwh.

Benguet 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 36414

10 projects · ₱76.9M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF CONCRETE ROAD-CAMP 3 TORRE-ANTAMOK-MANGGA-BELIS-PIMINGGAN-ANSAGAN PROPER ROAD IN SUPPORT OF CACAO AND COFFEE INDUSTRY, TUBA, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2021₱19.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BUED RIVER BASIN, CAMP 6 SECTION, TUBA, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2020₱12.6M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE -CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BUED RIVER BASIN CAMP 6, SECTION, TUBA, BENGUET, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2018₱9.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF CONCRETE ROAD - ALONG CAMP 3 TORRE-ANTAMOK-MANGGA-BELIS-PIMINGGAN-ANSAGAN PROPER ROAD IN SUPPORT OF CACAO AND COFFEE INDUSTRY, TUBA, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2020₱8.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF CONCRETE ROAD - ALONG PIMINGGAN-SAGUITLANG-LUBAS-DUNGON ROAD IN SUPPORT TO COFFEE, CACAO, BAMBOO, GOLD, LIVESTOCK,HIGH VALUE VEGETABLES AND FOOD PROCESSING, TUBA, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2020₱8.1M
Reported complete (DPWH)
No sat.

OFF-CARRIAGEWAY IMPROVEMENT: CONSTRUCTION OF LAYBYS ON SPECIFIC LOCATIONS ALONG MARCOS HI-WAY (S00432LZ) KO280+(-475) TO KO 281+755

Baguio City DEO, Cordillera Administrative Region

2019₱6.6M
Reported complete (DPWH)
View all 10 projects →

4. Implementation

Contract Amount

₱4,663,874.91

Progress

Reported complete (DPWH)

Start Date

September 17, 2020

Target End

December 25, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.