Buildings and Facilities17FC0241

CONST. OF TWO (2) STOREY SIX (6) CLASSROOM SCHOOL BLDG., BASUD CENTRAL SCHOOL, BASUD CAMS. NORTE

CONST. OF TWO (2) STOREY SIX (6) CLASSROOM SCHOOL BLDG., BASUD CENTRAL SCHOOL, BASUD CAMS. NORTE is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱14,621,147.47. Status: Reported complete (DPWH). Contractor on record: 128 DRAGON CONST AND SUPPLIES. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,402,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Danao River Flood Control Structure, Sta. 0+000 - Sta. 0+580 (R/S) and Sta. 0+210 - Sta. 0+580 (L/S), Brgys. Parang and Plaridel, Jose Panganiban, Camarines Norte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0009159

₱86,116.00 · FY2017

Released to Division of Camarines Norte (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

208 projects · ₱3.4B total · 2 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH ROAD ALONG DAET RIVER, BARANGAY

Region V, Region V

2025₱96.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF BINATAGAN RIVER CONTROL STRUCTURE W/ ROAD (PHASE I)BARA

Region V, Region V

2024₱93.6M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AL

Region V, Region V

2024₱86.8M
Reported complete (DPWH)

Construction of Flood Control Structure along Basud River, Barangay San Jose, Basud, Camarines Norte

BASUD (CAMARINES NORTE), CAMARINES NORTE, Region V

2024₱86.8M
Reported complete (DPWH)

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AL

Region V, Region V

2024₱86.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF MANGCAMAGONG -MATOOG-TOOG SEAWALL, BARANGAY MANGCAMAGONG, BASUD, CAMARINES NORTE AND BARANGAY MATOOG-TOOG, MERCEDES, CAMARINES NORTE

Camarines Norte DEO, Region V

2020₱74.9M
Reported complete (DPWH)
View all 208 projects →

4. Implementation

Contract Amount

₱14,621,147.47

Progress

Reported complete (DPWH)

Start Date

December 28, 2017

Target End

July 23, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.