PREVENTIVE MAINTENANCE-PRIMARY ROADS-SAYRE HIGHWAY K1527 + 000 - K1528 + 920, K1528 + 980 - K1529 + 007,K1531+484-K1535+089

PREVENTIVE MAINTENANCE-PRIMARY ROADS-SAYRE HIGHWAY K1527 + 000 - K1528 + 920, K1528 + 980 - K1529 + 007,K1531+484-K1535+089 is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱188,883,546.46. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: M MONTESCLAROS ENT INC. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱188,883,546.46

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

August 7, 2024

Target End

March 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.