Buildings and Facilities17FJ0015

LOCAL INFRA. PROG.(LIP) CONST. OF MULTI PURPOSE COVERED COURT (14M X 15M) BRGY.MAHAYAG, PLACER

LOCAL INFRA. PROG.(LIP) CONST. OF MULTI PURPOSE COVERED COURT (14M X 15M) BRGY.MAHAYAG, PLACER is a DPWH-tracked public work in Masbate 3rd DEO, Region V. Reported contract value: ₱1,899,929.95. Status: Reported complete (DPWH). Contractor on record: ALGIMAR CONST CORP 15232. Figures trace to dpwh.

Masbate 3rd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 15232

66 projects · ₱2.8B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0265+346-K0266+470, K0267+053-K0267+112, STA. ELENA, CAMARINES NORTE (1ST LEGISLATIVE DISTRICT)

Region V, Region V

2024₱136.8M
Past target date (DPWH On-Going)
No sat.

MFO1 - OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE-SECONDARY ROADS; MASBATE-CATAINGAN-PLACER ROAD, K0025+420 TO K0036+850 WITH EXCEPTIONS, CATAINGAN AND PLACER, MASBATE PROVINCE

Region V, Region V

2017₱132.6M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (GRAVEL TO CONC.) JCT. TAGBAK-LUBANG-LOOC RD.-BINACAS RD., KO009+625 (STA. 009+625.00)-KO012+273 (STA. 012+265.00), KO012+664 (STA. 012+664.00)-KO012+876 (STA. 012+880.00), KO012+976 (STA. 013+051.00)-KO014+172.80 (STA. 014+265.00), KO014+2

Region IV-B, Region IV-B

2016₱118.1M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-TAGKAWAYAN-LABO DIVERSION ROAD, LABO SECTION, CAMARINES NORTE, LABO, CAMARINES NORTE 1ST LEGISLATIVE DISTRICT

Region V, Region V

2023₱110.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION-CONSTRUCTION OF TALISAY COASTAL ROAD, MASBATE, SAN FERNANDO, MASBATE (1ST LEGISLATIVE DISTRICT)

Region V, Region V

2023₱99.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF SAN FERNANDO - SAN JACINTO - MONREAL ROAD, MASBATE.

Masbate 1st DEO, Region V

2023₱99.0M
Reported complete (DPWH)
View all 66 projects →

4. Implementation

Contract Amount

₱1,899,929.95

Progress

Reported complete (DPWH)

Start Date

February 10, 2017

Target End

July 9, 2017