Bridges16EH0096

REHABILITATION/MAJOR REPAIR OF PERMANENT TALABA BRIDGE (B00023SY) ALONG SIBUYAN CIRCUMFERENTIAL ROAD, MAGDIWANG, ROMBLON

REHABILITATION/MAJOR REPAIR OF PERMANENT TALABA BRIDGE (B00023SY) ALONG SIBUYAN CIRCUMFERENTIAL ROAD, MAGDIWANG, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱5,312,875.76. Status: Reported complete (DPWH). Contractor on record: MT GUITING-GUITING CONST 17412. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱5,312,875.76

Progress

Reported complete (DPWH)

Start Date

March 31, 2016

Target End

May 29, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.