Roads18FE0047

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM OFF-CARRIAGEWAY IMPROVEMENT-SECONDARY ROADS PILI-TIGAON-ALBAY BDRY. RD.-KO454+(-1016)-KO454+(-1016)

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM OFF-CARRIAGEWAY IMPROVEMENT-SECONDARY ROADS PILI-TIGAON-ALBAY BDRY. RD.-KO454+(-1016)-KO454+(-1016) is a DPWH-tracked public work in Camarines Sur 3rd DEO, Region V. Reported contract value: ₱28,984,727.00. Status: Reported complete (DPWH). Contractor on record: PHILWORKS CONST. Figures trace to dpwh.

Camarines Sur 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Improvement of Flood Control Structure along Caguiscan River, Loho, Lagonoy, Camarines Sur
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-18-0032622

₱0.00 · FY2018

Released to Division of Camarines Sur (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

81 projects · ₱6.4B total · 0 flags

Other projects by this contractor

CONSTRUCTION/IMPROVEMENT/UPGRADING OF FLOOD CONTROL ALONG SAN FRANCISCO RIVER, POLANGUI-OAS, ALBAY, POLANGUI, ALBAY 3RD LEGISLATIVE DISTRICT

Region V, Region V

2018₱281.5M
Reported complete (DPWH)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-REHABILITATION OF REVETMENT ALONG SAN FRANCISCO RIVER, UPSTREAM OF PONSO STEEL BR

Region V, Region V

2023₱280.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS-PILI DIVERSION ROAD-K0450+(-348)-K0450+(-122), K0450+(-099)-K0450+772.30, K04

Region V, Region V

2024₱203.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-MABOLO-ALMEDA BYPASS RD (PACKAGE 1), CAMARINES SUR, CAMARINES SUR (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2023₱193.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-REHABILITATION OF REVETMENT ALONG SAN FRANCISCO RIVER, DOWNSTREAM OF PONSO STEEL

Region V, Region V

2023₱187.0M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM -CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-MABOLO - ALMEDA BYPASS RD. (PACKAGE 2), CAMARINES SUR, NAGA CITY, CAMARINES SUR 3RD LEGISLATIVE DISTRICT

Region V, Region V

2023₱186.8M
Past target date (DPWH On-Going)
View all 81 projects →

4. Implementation

Contract Amount

₱28,984,727.00

Progress

Reported complete (DPWH)

Start Date

March 7, 2018

Target End

August 24, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.