Buildings and Facilities25DH0024

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ANTONIO, KALAYAAN, LAGUNA

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ANTONIO, KALAYAAN, LAGUNA is a DPWH-tracked public work in Laguna 1st DEO, Region IV-A. Reported contract value: ₱4,800,460.83. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: JOBEL ENT. Figures trace to dpwh.

Laguna 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of a Flood Mitigation Structure/River Control at Bulusukan River in Pila, Laguna
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Laguna 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,800,460.83

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 11, 2025

Target End

September 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.