Buildings and Facilities24HB0094

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP) -MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES -CONSTRUCTION OF MULTI-PURPOSE FACILITY, MABINI CENTRAL ELEMENTARY SCHOOL, POBLACION 2, MABINI, BOHOL

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP) -MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES -CONSTRUCTION OF MULTI-PURPOSE FACILITY, MABINI CENTRAL ELEMENTARY SCHOOL, POBLACION 2, MABINI, BOHOL is a DPWH-tracked public work in Bohol 3rd DEO, Region VII. Reported contract value: ₱4,928,759.31. Status: Reported complete (DPWH). Contractor on record: REBER ENT AND CONST. Figures trace to dpwh.

Bohol 3rd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control at Alejawan River ( Both Sides ) , Duero and Jagna, Bohol
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bohol 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

36 projects · ₱201.4M total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTI-PURPOSE FACILITIES - REHABILITATION OF DPWH BOHOL 3RD DISTRICT ENGINEERING OFFICE, GUINDULMAN, BOHOL

Bohol 3rd DEO, Region VII

2021₱24.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BATUAN, BOHOL

Bohol 3rd DEO, Region VII

2024₱9.9M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES REHABILITATION (COMPLETION) OF DPWH BOHOL 3RD DEO, GUINDULMAN, BOHOL

Bohol 3rd DEO, Region VII

2022₱9.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - JCT. (TER) ITUM - DUAY - PAYAO ROAD, DUERO LEADING TO CAMP VERDE NATURE PARK, DUERO

Bohol 3rd DEO, Region VII

2024₱9.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION OF ROAD, BRGY. CANDABONG, ANDA, BOHOL STA.0+000 - STA

Bohol 3rd DEO, Region VII

2022₱9.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT)- BAGUMBAYAN-ESTACA (PILAR)-CALUASAN-DA

Bohol 3rd DEO, Region VII

2022₱7.1M
Reported complete (DPWH)
View all 36 projects →

4. Implementation

Contract Amount

₱4,928,759.31

Progress

Reported complete (DPWH)

Start Date

April 12, 2024

Target End

August 14, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.