Buildings and Facilities17KB0090

CLUSTER I - CONSTRUCTION OF 1 UNIT, 1 STY - 2 CL AND 1 UNIT, 1 STY - 3 CL SB, DIGONGAN ES, DIGONGAN, KITAOTAO, BUKIDNON

CLUSTER I - CONSTRUCTION OF 1 UNIT, 1 STY - 2 CL AND 1 UNIT, 1 STY - 3 CL SB, DIGONGAN ES, DIGONGAN, KITAOTAO, BUKIDNON is a DPWH-tracked public work in Bukidnon 2nd DEO, Region X. Reported contract value: ₱7,431,757.08. Status: Reported complete (DPWH). Contractor on record: XY BUILDERS. Figures trace to dpwh.

Bukidnon 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱7,431,757.08

Progress

Reported complete (DPWH)

Start Date

February 5, 2018

Target End

July 9, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.