Flood Control and Drainage24CC0589

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, PACKAGE J, PUROK 4, BARANGAY SAN JUAN, BALAGTAS, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, PACKAGE J, PUROK 4, BARANGAY SAN JUAN, BALAGTAS, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱92,654,518.33. Status: Past target date (DPWH On-Going). Contractor on record: JB CONST AND SUPPLY INC FORMERLY:JB CONST AND SUPPLY. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Balagtas River, Barangay San Juan, Purok 4 - Purok 5, Balagtas, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bulacan 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱92,654,518.33

Progress

Past target date (DPWH On-Going)

Start Date

December 17, 2024

Target End

September 12, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.