Buildings and Facilities18KG0042

CONSTRUCTION OF MULTI PURPOSE BUILDING,VILLA ELENA,BARNAGAY POBLACION,KAPATAGAN,LANAO DEL NORTE

CONSTRUCTION OF MULTI PURPOSE BUILDING,VILLA ELENA,BARNAGAY POBLACION,KAPATAGAN,LANAO DEL NORTE is a DPWH-tracked public work in Lanao del Norte 2nd DEO, Region X. Reported contract value: ₱1,880,992.29. Status: Reported complete (DPWH). Contractor on record: RUSH REAL ESTATE BUILDERS. Figures trace to dpwh.

Lanao del Norte 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,880,992.29

Progress

Reported complete (DPWH)

Start Date

June 3, 2018

Target End

July 7, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.