Flood Control and Drainage18CM0024

CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, IMPROVEMENT OF TAMAYOK RIVER, SUBIC, ZAMBALES

CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, IMPROVEMENT OF TAMAYOK RIVER, SUBIC, ZAMBALES is a DPWH-tracked public work in Zambales 2nd DEO, Region III. Reported contract value: ₱47,025,532.79. Status: Reported complete (DPWH). Contractor on record: ORANI CONST AND SUPPLY CORP FORMERLY:ORANI BUILDERS. Figures trace to dpwh.

Zambales 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement of Tamayok River, Subic, Zambales
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Zambales 2nd DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱47,025,532.79

Progress

Reported complete (DPWH)

Start Date

February 9, 2018

Target End

October 21, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.