Flood Control and Drainage16BB0112

REPAIR/RESTORATION OF DAMAGED REVETMENT AT CENTRO LAL-LO, RIVER CONTROL LAL-LO, CAGAYAN, K0562+500-K0562+620

REPAIR/RESTORATION OF DAMAGED REVETMENT AT CENTRO LAL-LO, RIVER CONTROL LAL-LO, CAGAYAN, K0562+500-K0562+620 is a DPWH-tracked public work in Cagayan 1st DEO, Region II. Reported contract value: ₱7,242,325.11. Status: Reported complete (DPWH). Contractor on record: ST GERRARD CONST GEN CONTRACTOR. Figures trace to dpwh.

Cagayan 1st DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project along Cagayan River Basin, Barangay Bagumbayan, , Lal - lo Section, Lal - lo, Cagayan, 1st LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-16-0012658

₱3,968,267.00 · FY2016

Released to Soccsksargen Centers for Health Development To (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Other projects by this contractor

No sat.

PROPOSED CONSTRUCTION OF THE COURT OF TAX APPEALS (CTA) BUILDING III - 6 STOREY BUILDING WITH 1 LEVEL BASEMENT AND ROOF DECK

National Capital Region, National Capital Region

2022₱328.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS ROADS &/OR BRIDGES FR. THE NAT'L. ROAD/S LEAD. TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, BRGY. LIYANG, PILAR TO BRGY. BILOLO (PHASE 2), ORION, BAT.

Region III, Region III

2024₱305.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPL. SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FR. THE NAT'L. ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES, CONST. OF ROAD, BRGY. ALAS-ASIN IPAG (PHASE 2), MARIVE

Region III, Region III

2024₱304.2M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM- CONSTRUCTION OF MISSING LINKS/NEW ROADS- MINDORO ISLAND CIRCUMFERENTIAL ROAD (PUERTO GALERA-ABRA DE ILOG), PACKAGE C, OCCIDENTAL MINDORO

Region IV-B, Region IV-B

2023₱268.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LAOAG-SAN NICOLAS BYPASS ROAD (SAN NICOLAS SECTION), ILOCOS NORTE

Region I, Region I

2022₱260.5M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND- MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239- INSTALLATUION OF ROADWAY LIGHTING STRUCTURE ALONG PUERTO PRINCESA SOUTH ROAD, K0095+000-K0112+669 (INTERMITTENT SECTIONS), PALAWAN

Region IV-B, Region IV-B

2024₱241.2M
Reported complete (DPWH)
View all 545 projects →

4. Implementation

Contract Amount

₱7,242,325.11

Progress

Reported complete (DPWH)

Start Date

January 26, 2017

Target End

April 16, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.