Buildings and Facilities19FO0156

CONSTRUCTION OF MPB (COVERED COURT) STA. CRUZ, LIGAO, ALBAY

CONSTRUCTION OF MPB (COVERED COURT) STA. CRUZ, LIGAO, ALBAY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱4,769,345.87. Status: Reported complete (DPWH). Contractor on record: LIENEL BUILDERS AND SUPPLY. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,769,345.87

Progress

Reported complete (DPWH)

Start Date

October 3, 2019

Target End

March 30, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.