Buildings and Facilities17DF0055

LOCALLY-FUNDED PROJECTS, LOCAL INFRASTRUCTURE PROGRAM (LIP), SCHOOL BUILDINGS, CONSTRUCTION OF 4 SPED CLASSROOM BUILDING - IMUS PILOT ELEMENTARY SCHOOL, NUEVO AVENUE, POBLACION 1A, IMUS, CAVITE

LOCALLY-FUNDED PROJECTS, LOCAL INFRASTRUCTURE PROGRAM (LIP), SCHOOL BUILDINGS, CONSTRUCTION OF 4 SPED CLASSROOM BUILDING - IMUS PILOT ELEMENTARY SCHOOL, NUEVO AVENUE, POBLACION 1A, IMUS, CAVITE is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱2,969,943.37. Status: Reported complete (DPWH). Contractor on record: 747 BUILDERS. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control in Taguilid River, Brgy. Marulas Section, Kawit, Cavite
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0009159

₱86,116.00 · FY2017

Released to Division of Camarines Norte (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

125 projects · ₱1.1B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION OF ROAD, BARANGAY STA.CLARA

Cavite 1st DEO, Region IV-A

2023₱28.9M
Reported complete (DPWH)
No sat.

CONCRETING OF BARANGAY PARADISE III FMR, BARANGAY PARADISE III, SAN JOSE DEL MONTE CITY, BULACAN

Bulacan 2nd DEO, Region III

2023₱24.9M
Reported complete (DPWH)
No sat.

LOCAL PROGRAMLOCAL INFRASTRUCTURE PROGRAMLOCAL ROADS AND BRIDGESLOCAL ROADSASPHALT OVERLAY, ARNALDO HIGHWAY, BARANGAY SAN FRANCISCO, GENERAL TRIAS CITY, CAVITE

Cavite 1st DEO, Region IV-A

2021₱24.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- TERTIARY ROADS-2ND STREET (FROM BONIFACIO DRIVE TO BASECO AREA)

South Manila DEO, National Capital Region

2024₱24.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1, ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING, PRIMARY ROADS, KAWIT-NOVELETA DIVERSION RD. - K0022+(-364) - K0022+(-299), K0022+(-224) - K0022+(-167), K0022+(-167) - K0022+(-106), K0022

Cavite 1st DEO, Region IV-A

2020₱23.0M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL BRIDGES - CONSTRUCTION OF GREGORIO LUNA BRIDGE AT LIGTONG 4, ROSARIO, CAVITE

Cavite 1st DEO, Region IV-A

2019₱22.8M
Reported complete (DPWH)
View all 125 projects →

4. Implementation

Contract Amount

₱2,969,943.37

Progress

Reported complete (DPWH)

Start Date

April 10, 2017

Target End

October 6, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.