Buildings and Facilities24PA0150

CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING, BULBULALA ELEMENTARY SCHOOL, BRGY. BULBULALA, LA PAZ, ABRA

CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING, BULBULALA ELEMENTARY SCHOOL, BRGY. BULBULALA, LA PAZ, ABRA is a DPWH-tracked public work in Abra DEO, Cordillera Administrative Region. Reported contract value: ₱4,778,289.61. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: 739 BUILDERS 31174. Figures trace to dpwh.

Abra DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Malabbaga Flood Control Structure, Malabbaga, La Paz, Abra
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Abra DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 31174

598 projects · ₱12.8B total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF DUGONG BRIDGE, BUCAY, ABRA

Abra DEO, Cordillera Administrative Region

2024₱139.7M
Past target date (DPWH On-Going)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVER, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ABRA MAJOR RIVER BASIN (PHASE II), BARANGAY BA

Abra DEO, Cordillera Administrative Region

2023₱138.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECT ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHABILITATION OF POBLACION-GAYAMAN ROAD, LUBA, ABRA

Abra DEO, Cordillera Administrative Region

2024₱138.0M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF MISSING LINKS/NEW ROADS, BESAO-TUBO (VIA TAMBOAN) ROAD, PACKAGE A, ABRA

Abra DEO, Cordillera Administrative Region

2023₱115.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ABRA RIVER, BARANGAY PANTAY AND BARANGAY TAMURONG, CAOAYAN, ILOCOS SUR

Ilocos Sur 1st DEO, Region I

2025₱112.3M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF ROAD, BARANGAY CARDONA, DOLORES, ABRA

Abra DEO, Cordillera Administrative Region

2023₱99.0M
Reported complete (DPWH)
View all 598 projects →

4. Implementation

Contract Amount

₱4,778,289.61

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

July 3, 2024

Target End

October 31, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.