Roads22EB0040

CONSTRUCTION OF CONCRETE ROAD - ACCESS ROAD LEADING TO LUYANG BAGA CAVE, ABRA DE ILOG, OCCIDENTAL MINDORO

CONSTRUCTION OF CONCRETE ROAD - ACCESS ROAD LEADING TO LUYANG BAGA CAVE, ABRA DE ILOG, OCCIDENTAL MINDORO is a DPWH-tracked public work in Mindoro Occidental DEO, Region IV-B. Reported contract value: ₱48,420,630.10. Status: Reported complete (DPWH). Contractor on record: ST GERRARD CONST GEN CONTRACTOR. Figures trace to dpwh.

Mindoro Occidental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Callejon Flood Control Structure, Abra de Ilog, Occidental Mindoro
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Mindoro Occidental DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Other projects by this contractor

No sat.

PROPOSED CONSTRUCTION OF THE COURT OF TAX APPEALS (CTA) BUILDING III - 6 STOREY BUILDING WITH 1 LEVEL BASEMENT AND ROOF DECK

National Capital Region, National Capital Region

2022₱328.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS ROADS &/OR BRIDGES FR. THE NAT'L. ROAD/S LEAD. TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, BRGY. LIYANG, PILAR TO BRGY. BILOLO (PHASE 2), ORION, BAT.

Region III, Region III

2024₱305.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPL. SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FR. THE NAT'L. ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES, CONST. OF ROAD, BRGY. ALAS-ASIN IPAG (PHASE 2), MARIVE

Region III, Region III

2024₱304.2M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM- CONSTRUCTION OF MISSING LINKS/NEW ROADS- MINDORO ISLAND CIRCUMFERENTIAL ROAD (PUERTO GALERA-ABRA DE ILOG), PACKAGE C, OCCIDENTAL MINDORO

Region IV-B, Region IV-B

2023₱268.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LAOAG-SAN NICOLAS BYPASS ROAD (SAN NICOLAS SECTION), ILOCOS NORTE

Region I, Region I

2022₱260.5M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND- MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239- INSTALLATUION OF ROADWAY LIGHTING STRUCTURE ALONG PUERTO PRINCESA SOUTH ROAD, K0095+000-K0112+669 (INTERMITTENT SECTIONS), PALAWAN

Region IV-B, Region IV-B

2024₱241.2M
Reported complete (DPWH)
View all 545 projects →

4. Implementation

Contract Amount

₱48,420,630.10

Progress

Reported complete (DPWH)

Start Date

March 14, 2022

Target End

July 10, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.