Buildings and Facilities18CG0291

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT DOLORES, MACABACLE, MAGLIMAN AND MALIWALU BACOLOR, PAMPANGA (R.A. 9506-BACOLOR REHABILITATION ACT)

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT DOLORES, MACABACLE, MAGLIMAN AND MALIWALU BACOLOR, PAMPANGA (R.A. 9506-BACOLOR REHABILITATION ACT) is a DPWH-tracked public work in Pampanga 1st DEO, Region III. Reported contract value: ₱7,424,470.00. Status: Reported complete (DPWH). Contractor on record: BPDG CONST CORP FORMERLY: BPDG CONST. Figures trace to dpwh.

Pampanga 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Channel and Slope Protection and Malisik River Control, Candaba, Pampanga
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Pampanga 1st DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

115 projects · ₱668.8M total · 0 flags

Other projects by this contractor

View all 115 projects →

4. Implementation

Contract Amount

₱7,424,470.00

Progress

Reported complete (DPWH)

Start Date

August 22, 2018

Target End

December 19, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.