Buildings and Facilities21PA0262

CONSTRUCTION OF 4-STOREY, 8-CLASSROOM SCHOOL BUILDING, ABRA HIGH SCHOOL, BANGUED, ABRA

CONSTRUCTION OF 4-STOREY, 8-CLASSROOM SCHOOL BUILDING, ABRA HIGH SCHOOL, BANGUED, ABRA is a DPWH-tracked public work in Abra DEO, Cordillera Administrative Region. Reported contract value: ₱18,688,058.45. Status: Reported complete (DPWH). Contractor on record: R A FANGLAYAN RAF GEN CONST INC FORMERLY:RAF GEN CONST. Figures trace to dpwh.

Abra DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱1,602,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Ba±acao Flood Contro, Sta. 33+024 - Sta. 33+296, Bangued, Abra
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Abra DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

211 projects · ₱3.0B total · 0 flags

4. Implementation

Contract Amount

₱18,688,058.45

Progress

Reported complete (DPWH)

Start Date

October 20, 2021

Target End

June 3, 2022

5. Audit