Construction of Flood Mitigation Structure22ID0052

Construction of Hibuga Flood Control Structure and Drainage, Hibuga River Basin, Sta. 0+106 - Sta. 0+677, Brgy. General Luna, Mayorga, Leyte

Construction of Hibuga Flood Control Structure and Drainage, Hibuga River Basin, Sta. 0+106 - Sta. 0+677, Brgy. General Luna, Mayorga, Leyte is a DPWH-tracked public work in MAYORGA (LEYTE), LEYTE, Region VIII. Reported contract value: ₱48,307,483.94. Status: Reported complete (DPWH). Contractor on record: FAIRCHILD BUILDERS & DEVELOPERS INC. Figures trace to sumbong.

MAYORGA (LEYTE), LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Hibuga Flood Control Structure and Drainage, Hibuga River Basin, Sta. 0+106 - Sta. 0+677, Brgy. General Luna, Mayorga, Leyte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002647

₱550,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0006795

₱50,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003176

₱50,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-22-0005719

₱20,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003040

₱2,500,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

42 projects · ₱3.3B total · 2 flags

Other projects by this contractor

No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONSTRUCTION OF ROAD, BURAUEN, LEYTE

Region VIII, Region VIII

2022₱286.3M
Past target date (DPWH On-Going)
No sat.

CLUSTER 1: 1. CONSTRUCTION OF ROCK GUARD SLOPE PROTECTION ALONG BURAUEN - MAHAGNAO ROAD, K0988+780 - K0989+020, BURAUEN, LEYTE; AND TWO (2) OTHER LOCATIONS IN BURAUEN, LEYTE

Region VIII, Region VIII

2020₱283.4M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - BURAUEN - MAHAGNAO RD. - K0989+685 - K0989+810, BURAUEN, LEYTE

Region VIII, Region VIII

2021₱144.7M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - BURAUEN - MAHAGNAO RD. - K0989+560 - K0989+685, BURAUEN, LEYTE

Region VIII, Region VIII

2021₱144.7M
Reported complete (DPWH)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - ROAD OPENING AND CONCRETING OF BURAUEN SOUTHEAST SEMI-CIRCUMFERENTIAL ROAD TRAVERSING BRGY. POBLACION

Region VIII, Region VIII

2023₱144.7M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF (RCDG) REINFORCED CONCRETE DECK GIRDER BRIDGE FROM BARANGAY MAHAGN

Region VIII, Region VIII

2024₱144.7M
Past target date (DPWH On-Going)
View all 42 projects →

4. Implementation

Contract Amount

₱48,307,483.94

Progress

Reported complete (DPWH)

Start Date

March 1, 2022

Target End

November 13, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.