Construction of Flood Mitigation Structure21DO0055

Construction of Riprap in Bautista Creek Banlik Sub Urban Village, San Jose, Rodriguez, Rizal

Construction of Riprap in Bautista Creek Banlik Sub Urban Village, San Jose, Rodriguez, Rizal is a DPWH-tracked public work in RIZAL, Region IV-A. Reported contract value: ₱5,940,000.00. Status: Reported complete (DPWH). Contractor on record: DOUBLE 12 CONST & SUPPLY. Figures trace to sumbong.

RIZAL, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, Barangay San Jose, Rodriguez, Rizal
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0012598

₱142,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013376

₱5,000,000.00 · FY2021

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱5,940,000.00

Progress

Reported complete (DPWH)

Start Date

September 5, 2022

Target End

March 3, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.