GAA 2023 OO-223PA0024

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVER, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ABRA RIVER BASIN (PHASE II), CALABA, BANGUED,

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVER, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ABRA RIVER BASIN (PHASE II), CALABA, BANGUED, is a DPWH-tracked public work in Abra DEO, Cordillera Administrative Region. Reported contract value: ₱96,497,672.25. Status: Past target date (DPWH On-Going). Contractor on record: NORTH TECH BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Abra DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱96,497,672.25

Progress

Past target date (DPWH On-Going)

Start Date

April 11, 2023

Target End

December 7, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.