Water Provision and Storage22GN0095

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM - RAINWATER COLLECTOR IN PUBLIC FACILITIES 1. MAKILAN ELEMENTARY SCHOOL, BRGY. TABUNAN, BAGO CITY, NEGROS OCCIDENTAL 2. BRGY. SAN JUAN, PONTEVEDRA, NEGROS OCCI

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM - RAINWATER COLLECTOR IN PUBLIC FACILITIES 1. MAKILAN ELEMENTARY SCHOOL, BRGY. TABUNAN, BAGO CITY, NEGROS OCCIDENTAL 2. BRGY. SAN JUAN, PONTEVEDRA, NEGROS OCCI is a DPWH-tracked public work in Negros Occidental 4th DEO, Negros Island Region. Reported contract value: ₱4,135,098.00. Status: Reported complete (DPWH). Contractor on record: SILVERRIA CONST AND CONST SUPPLY CO OPC. Figures trace to dpwh.

Negros Occidental 4th DEO, Negros Island Region
Region: Negros Island Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱7,700,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures along Marayo River, Brgy. San Juan, Pontevedra, Negros Occidental
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Negros Occidental 4th DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

22GN0095 - Construction/Rehabilitation of Water Su

₱4,135,098.00 · SILVERRIA CONSTRUCTION AND CONSTRUCTION SUPPLY , OPC

4. Implementation

Contract Amount

₱4,135,098.00

Progress

Reported complete (DPWH)

Start Date

December 1, 2022

Target End

February 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.