Roads20IB0021

CONSTRUCTION/UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS, JCT. BUENAVISTA - LAWAAN - MARABUT ROAD, K0955+000 - K0955+213, K0955+811 - K0956+055, K0961+488 - K0961+813, K0962+342 - K0962+551, K0962+575 - K0962+700, K0969+55

CONSTRUCTION/UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS, JCT. BUENAVISTA - LAWAAN - MARABUT ROAD, K0955+000 - K0955+213, K0955+811 - K0956+055, K0961+488 - K0961+813, K0962+342 - K0962+551, K0962+575 - K0962+700, K0969+55 is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱12,735,265.90. Status: Reported complete (DPWH). Contractor on record: PABLO S LABASBAS CONST CORP FORMERLY: PABLOS LABASBAS CONST CORP. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱14,468,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Jct. Buenavista-Lawaan-Marabut Road, K0978+200-K0979+100, Brgy. Coticot, Giporlos, Eastern Samar
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Eastern Samar DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

20IB0021 - Construction/Upgrading/Rehabilitation o

₱12,096,202.52 · PABLO S. LABASBAS CONSTRUCTION

Contractor

B

515 projects · ₱13.3B total · 0 flags

Other projects by this contractor

No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BRGY. SUROK - GAHOY - SAPAO, GUIUAN, EASTERN SAMAR

Region VIII, Region VIII

2023₱144.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS TACLOBAN - STA. FE - SAN MIGUEL ROAD, LEYTE

Region VIII, Region VIII

2023₱143.5M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE ALONG ASUNCION - BENIT SECTION, MALITBOG, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2024₱120.5M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY NUEVA ESPERANZA, HINUNANGAN, SOUTHERN LEYTE

Southern Leyte 2nd DEO, Region VIII

2025₱105.6M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING SECONDARY ROADS, WRIGHT - TAFT - BORONGAN RD (SM00172SM)K0875+667 - K0876+511, K0877+525 - K0878+256, K0878+800 - K0879+389

Eastern Samar DEO, Region VIII

2025₱104.8M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - BAGAHUPI - BABATNGON - STA CRUZ - BARUGO - CARIGARA RD. - (S00066LT) K0927+(-348) - K0927+(-310), LEYTE 1ST LD

Region VIII, Region VIII

2023₱101.2M
Reported complete (DPWH)
View all 515 projects →

4. Implementation

Contract Amount

₱12,735,265.90

Progress

Reported complete (DPWH)

Start Date

February 17, 2020

Target End

August 14, 2020

5. Audit