Buildings and Facilities17ED0072

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DEL PILAR, NAUJAN, ORIENTAL MINDORO

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DEL PILAR, NAUJAN, ORIENTAL MINDORO is a DPWH-tracked public work in Mindoro Oriental DEO, Region IV-B. Reported contract value: ₱1,898,630.11. Status: Reported complete (DPWH). Contractor on record: 876 CONST. Figures trace to dpwh.

Mindoro Oriental DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control Project, Naujan, Oriental Mindoro
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0000040

₱213,291.00 · FY2017

Released to 0008 - Regional Office VIII Ter Oli (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,898,630.11

Progress

Reported complete (DPWH)

Start Date

April 17, 2017

Target End

June 15, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.