BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ARINGAY RIVER BASIN, PACKAGE 2, BARANGAY ANDUYAN, TUBAO, LA UNION is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱57,621,997.33. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: VILLAR GEN CONST AND SUPPLIES. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

493 projects · ₱8.0B total · 0 flags

4. Implementation

Contract Amount

₱57,621,997.33

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 24, 2025

Target End

October 9, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.