GAA 2025 OO-225FL0006

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY CARRIEDO, GUBAT, SORSOGON

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY CARRIEDO, GUBAT, SORSOGON is a DPWH-tracked public work in Sorsogon 2nd DEO, Region V. Reported contract value: ₱107,645,889.20. Status: Past target date (DPWH On-Going). Contractor on record: CENTERWAYS CONST AND DEVELOPMENT INC. Figures trace to dpwh.

Sorsogon 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Macabari, Barcelona, Sorsogon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Sorsogon 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

309 projects · ₱22.7B total · 8 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM-TIKAS)-CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE PROJECTS

Region V, Region V

2024₱263.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-SPECIAL ROAD FUND-MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG JCT. PUTIAO-PILAR-DONSOL ROAD-K0549+000 -K0554+000 PILAR, SORSOGON

Sorsogon DEO, Region V

2024₱242.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF CADAC-AN RIVER FLOOD MITIGATION STRUCTURE, BARANGAY GUMAPIA, IROSIN, SORSOGON

Sorsogon 2nd DEO, Region V

2025₱188.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, NAGA CITY, CAMARINES SUR, NAGA CITY, CAMARINES SUR (3RD LEGISLATIVE DISTRI

Region V, Region V

2024₱184.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, INAMIGAN RIVER, BARANGAY PAOLBO,

Region V, Region V

2025₱169.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM(CSSP)-BASIC INFRASTRUCTURE PROGRAM(BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, PRES. CORY AQUINO BOULEVARD EXTENSION, TALISA

Region V, Region V

2023₱153.4M
Reported complete (DPWH)
View all 309 projects →

4. Implementation

Contract Amount

₱107,645,889.20

Progress

Past target date (DPWH On-Going)

Start Date

February 21, 2025

Target End

February 3, 2026

5. Audit