Roads16LG0007

CONCRETING OF ROAD, JUNCTION BRGY. DAWAN TO BRGY. MACAMBOL, MATI, DAVAO ORIENTAL

CONCRETING OF ROAD, JUNCTION BRGY. DAWAN TO BRGY. MACAMBOL, MATI, DAVAO ORIENTAL is a DPWH-tracked public work in Davao Oriental 2nd DEO, Region XI. Reported contract value: ₱19,481,703.84. Status: Reported complete (DPWH). Contractor on record: COASTLAND CONST. Figures trace to dpwh.

Davao Oriental 2nd DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱19,481,703.84

Progress

Reported complete (DPWH)

Start Date

March 7, 2016

Target End

July 5, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.