Rehabilitation / Major Repair of Flood Control Structure22CG0043

Rehabilitation of Eroded Pampanga River Bank along Barangay San Juan, San Luis, Pampanga

Rehabilitation of Eroded Pampanga River Bank along Barangay San Juan, San Luis, Pampanga is a DPWH-tracked public work in SAN LUIS (PAMPANGA), PAMPANGA, Region III. Reported contract value: ₱83,810,211.36. Status: Reported complete (DPWH). Contractor on record: NULAS BUILDERS / EDDMARI CONST & TRADING. Figures trace to sumbong.

SAN LUIS (PAMPANGA), PAMPANGA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Mitigation Structure along Sapang Are Creek, Apalit, Pampanga
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002819

₱16,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0003564

₱8,195,323.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002913

₱1,246,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0003565

₱754,796.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0005827

₱130,962.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0007602

₱856,088.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱83.8M total · 0 flags

4. Implementation

Contract Amount

₱83,810,211.36

Progress

Reported complete (DPWH)

Start Date

March 3, 2022

Target End

October 28, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.