Roads25IG0071

CONCRETING OF BRGY. CALUMPANG TO BRGY. SAN VICENTE TO BRGY. ESPERANZA FMR, BRGYS. CALUMPANG, SAN VICENTE AND ESPERANZA, MATALOM, LEYTE

CONCRETING OF BRGY. CALUMPANG TO BRGY. SAN VICENTE TO BRGY. ESPERANZA FMR, BRGYS. CALUMPANG, SAN VICENTE AND ESPERANZA, MATALOM, LEYTE is a DPWH-tracked public work in Leyte 5th DEO, Region VIII. Reported contract value: ₱14,916,650.00. Status: Past target date (DPWH On-Going). Contractor on record: JDR CONST. Figures trace to dpwh.

Leyte 5th DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure and Drainage System, Barangay San Miguel, Tanauan, Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Leyte 5th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,916,650.00

Progress

Past target date (DPWH On-Going)

Start Date

June 19, 2025

Target End

September 27, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.