Buildings and Facilities16IA0015

CONSTRUCTION OF GYM PHASE I, BRGY. PALANAY CAIBIRAN, BILIRAN LONE DISTRICT, BILIRAN PROVINCE

CONSTRUCTION OF GYM PHASE I, BRGY. PALANAY CAIBIRAN, BILIRAN LONE DISTRICT, BILIRAN PROVINCE is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱1,892,000.00. Status: Reported complete (DPWH). Contractor on record: W B ALAGAO CONST. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱8,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bagongbong Flood Control (Revetment) along Biliran Circumferential Road, Phase II, Almeria, Biliran Province
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0026880

₱0.00 · FY2016

Released to Catubig Valley National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,892,000.00

Progress

Reported complete (DPWH)

Start Date

March 1, 2016

Target End

June 13, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.