Roads24DE0204

CONCRETING OF BRGY. SAN NICOLAS TO BRGY. APAR FMR, BRGY. SAN NICOLAS, LOBO, BATANGAS

CONCRETING OF BRGY. SAN NICOLAS TO BRGY. APAR FMR, BRGY. SAN NICOLAS, LOBO, BATANGAS is a DPWH-tracked public work in Batangas 2nd DEO, Region IV-A. Reported contract value: ₱6,965,000.00. Status: Reported complete (DPWH). Contractor on record: LLEB CONST AND TRADING. Figures trace to dpwh.

Batangas 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Sitio San Vicente ( Upstream ) , Brgy. Libjo, Batangas City, Batangas
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Batangas 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

70 projects · ₱589.3M total · 0 flags

4. Implementation

Contract Amount

₱6,965,000.00

Progress

Reported complete (DPWH)

Start Date

June 19, 2024

Target End

November 19, 2024

5. Audit